Video: Animation of Chickamauga Lock Replacment
Here's a detailed design specification
Project Abstract:
- A concrete aggregate problem will cause the current lock to be closed without aggressive maintenance.
- Construction was initiated in summer 2007, and a Road and Bridge Relocation contract ($16M) was completed in FY07.
- $27 million was available in FY07 for cofferdam construction and lock design.
- $35 million is in the FY08 budget to continue construction and design.
- Construction of the new lock will follow the 34-month cofferdam contract.